         We are pleased to inform you that as of 15 June 2010, overall project accomplishment is 30.00%. For Tower 1, foundation works is complete with ongoing concreting at 31/F and plastering and CHB laying at 24/F. Other ongoing works includes fabrication and installation of concrete precast, rubbed concreting works, rebar testing, electrical wiring, roughing-ins, and installation of devices, metal and mechanical works, and installation and pipe sleeving works for plumbing, electrical and fire-protection lines. For Tower 2, concreting works are ongoing at 3/F.


CONSTRUCTION REPORT AS OF 15 JUNE 2010


ITEM
% OF COMPLETION
REMARKS
Excavation Works 100.00% Completed
Civil / Structural Works

79.81%

On Schedule
Electrical Works 16.22% On Schedule
Plumbing Works 13.35% On Schedule
Fire Protection Works 31.68% On Schedule
Mechanical Works 10.83% On Schedule
                                                                                                          *Tower 1
 

 

For Inquires
Eastwood LeGrand
188 E. Rodriguez Jr. Avenue (C-5),
Bagumbayan Quezon City,
Philippines 1110

Tel. No.: (+632) 421-3961 to 64
Fax No.:(+632) 421-3960
  Customer Hotline:

421-0000