A New Chapter In Gracious Living.

         We are pleased to inform you that as of 15 April 2013, the overall project accomplishment for Eastwood Le Grand is 93.35% and 93.61% for Tower 1 & 2 respectively. For Tower 1, civil/structural works is substantially complete, fabrication and installation of pipe guard railing is on going at P/4. For Fire-protection works on going works includes fabrication and installation of supports and rectification and adjustments of side wall sprinkler heads. The project is on progress with accordance to its schedule.

 

CONSTRUCTION REPORT AS OF 15 APRIL 2013


ITEM
% OF COMPLETION
REMARKS
Excavation Works 100.00% Completed
Civil / Structural Works

98.94%

On Schedule
Architectural Works 86.96% On Schedule
Electrical Works 91.80% On Schedule
Plumbing Works 92.88% On Schedule
Fire Protection Works 95.10% On Schedule
Mechanical Works 94.64% On Schedule
Waterproofing Works 43.60% On Schedule
Elevator Works - -
Painting Works 47.93% On Schedule
                                                                                                          *Tower 1 & 2

              

 

For Inquires
Eastwood LeGrand
188 E. Rodriguez Jr. Avenue (C-5),
Bagumbayan Quezon City,
Philippines 1110

Tel. No.: (+632) 421-3961 to 64
Fax No.:(+632) 421-3960
  Customer Hotline:

421-0000