We are pleased to inform you that as of 15 June 2010, overall project accomplishment is 30.00%. For Tower 1, foundation works is complete with ongoing concreting at 31/F and plastering and CHB laying at 24/F. Other ongoing works includes fabrication and installation of concrete precast, rubbed concreting works, rebar testing, electrical wiring, roughing-ins, and installation of devices, metal and mechanical works, and installation and pipe sleeving works for plumbing, electrical and fire-protection lines. For Tower 2, concreting works are ongoing at 3/F.
CONSTRUCTION REPORT AS OF 15 JUNE 2010
ITEM |
% OF COMPLETION
|
REMARKS |
| Excavation Works | 100.00% | Completed |
| Civil / Structural Works |
79.81% |
On Schedule |
| Electrical Works | 16.22% | On Schedule |
| Plumbing Works | 13.35% | On Schedule |
| Fire Protection Works | 31.68% | On Schedule |
| Mechanical Works | 10.83% | On Schedule |
*Tower 1