We are pleased to inform you that as of 15 April 2013, the overall project accomplishment for Eastwood Le Grand is 93.35% and 93.61% for Tower 1 & 2 respectively. For Tower 1, civil/structural works is substantially complete, fabrication and installation of pipe guard railing is on going at P/4. For Fire-protection works on going works includes fabrication and installation of supports and rectification and adjustments of side wall sprinkler heads. The project is on progress with accordance to its schedule.
CONSTRUCTION REPORT AS OF 15 APRIL 2013
ITEM |
% OF COMPLETION
|
REMARKS |
| Excavation Works | 100.00% | Completed |
| Civil / Structural Works |
98.94% |
On Schedule |
| Architectural Works | 86.96% | On Schedule |
| Electrical Works | 91.80% | On Schedule |
| Plumbing Works | 92.88% | On Schedule |
| Fire Protection Works | 95.10% | On Schedule |
| Mechanical Works | 94.64% | On Schedule |
| Waterproofing Works | 43.60% | On Schedule |
| Elevator Works | - | - |
| Painting Works | 47.93% | On Schedule |
*Tower 1 & 2