Construction Updates
Construction Report as of October 2010
October 27, 2010, 7:19 am

We are pleased to inform you that as of 15 October 2010, the overall project accomplishment for One Central Park (Tower 3) and Eastwood Park Hotel & Residential Suites (Tower 4) are 100% and 91.90% respectively. For Tower 4, remaining works reworks on swimming pool area, painting, installation of electrical, mechanical and plumbing fixtures, waterproofing, elevator works, testing of fire alarm systems, Wi-Fi and telephone system commissioning, and punchlisting works on interior finishes.

CONSTRUCTION REPORT AS OF 15 OCTOBER 2010

ITEM

% OF COMPLETION

REMARKS

Excavation / Structural Works

100.00% Completed

Civil / Architectural Works

100.00% Completed

Interior Works

90.00% On Schedule

Mechanical Works

99.00% On Schedule

Elevator Works

79.75% On Schedule

Sanitary / Plumbing Works

93.10% On Schedule

Fire Protection Works

96.50% On Schedule

Electrical & Auxiliary Works

88.92% On Schedule

Painting Works

71.58% On Schedule

Waterproofing Works

90.00% On Schedule

Glass & Aluminum Works

99.35% On Schedule
*Tower 4