 | Construction Report as of October 2010October 27, 2010, 7:19 am We are pleased to inform you that as of 15 October 2010, the overall project accomplishment for One Central Park (Tower 3) and Eastwood Park Hotel & Residential Suites (Tower 4) are 100% and 91.90% respectively. For Tower 4, remaining works reworks on swimming pool area, painting, installation of electrical, mechanical and plumbing fixtures, waterproofing, elevator works, testing of fire alarm systems, Wi-Fi and telephone system commissioning, and punchlisting works on interior finishes.
CONSTRUCTION REPORT AS OF 15 OCTOBER 2010
|
ITEM
|
% OF COMPLETION
|
REMARKS
|
|
Excavation / Structural Works
|
100.00% |
Completed |
|
Civil / Architectural Works
|
100.00% |
Completed |
|
Interior Works
|
90.00% |
On Schedule |
|
Mechanical Works
|
99.00% |
On Schedule |
|
Elevator Works
|
79.75% |
On Schedule |
|
Sanitary / Plumbing Works
|
93.10% |
On Schedule |
|
Fire Protection Works
|
96.50% |
On Schedule |
|
Electrical & Auxiliary Works
|
88.92% |
On Schedule |
|
Painting Works
|
71.58% |
On Schedule |
|
Waterproofing Works
|
90.00% |
On Schedule |
|
Glass & Aluminum Works
|
99.35% |
On Schedule |
*Tower 4
| |