Construction Updates
Construction Report as of June 2010
June 15, 2010, 3:44 am

We are pleased to inform you that as of 15 June 2010, the overall project accomplishment for One Central Park (Tower 3) and Eastwood Park Hotel & Residential Suites (Tower 4) are 94.04% and 88.09% respectively. On-going works for Tower 3 includes tile works, dry wall partitioning, ceiling works, installation of bedroom closets, kitchen cabinets, lavatory countertop, and laminated flooring, plumbing and electrical works, glass & aluminum works, and painting while fire protection works is substantially complete. For Tower 4, installation of aluminum doors/windows & glass works is almost complete. Other works includes painting, installation of electrical and plumbing fixtures, doors & jambs, waterproofing, elevator works, installation of fire alarm systems, installation of kitchen equipments, vanity counter, curtains at guestroom floors, carpet flooring, stainless railings at pool deck, and interior finishing works on fitness center

CONSTRUCTION REPORT AS OF 15 JUNE 2010

ITEM

% OF COMPLETION

REMARKS

Excavation / Structural Works

100.00% Completed

Civil / Architectural Works

98.70% On Schedule

Interior Works

85.00% On Schedule

Mechanical Works

93.54% On Schedule

Elevator Works

75.55% On Schedule

Sanitary / Plumbing Works

92.93% On Schedule

Fire Protection Works

95.23% On Schedule

Electrical & Auxiliary Works

77.55% On Schedule

Painting Works

70.13% On Schedule

Waterproofing Works

89.78% On Schedule

Glass & Aluminum Works

98.00% On Schedule
*Tower 3 & 4
Photos
 
Click on thumbnails to view larger photos.